Our Ref: PL-202102011
Drainage Services Department
Special Duty Division
42/F, Revenue Tower, 5 Gloucester Road,
Wan Chai, Hong Kong.
Attention: Ms. Wing W.Y. Law
4 February 2021
Dear Wing,
Sewerage Works at Po Toi O
Construction Works Schedule and Location Plans
I refer to the email from the ET concerning the captioned. I have no adverse comment on the
Construction Works Schedule and Location Plans for Port Shelter Phase 3 Po Toi O sewerage
Treatment Plant (Issue 3) and hereby verify this document in accordance with Condition 2.10 of the
Environmental Permit with permit No EP-516/2016.
Yours faithfully,
F.C. Tsang
Independent Environmental Checker
Unit C, 11/F., Ford Glory Plaza,
Nos. 37-39 Wing Hong Street,
Cheung Sha Wan, Kowloon, HK