Project No. 1825
Monthly Environmental Monitoring & Audit Report for Port Shelter Phase 3, Po Toi O Sewerage Treatment Plant
24-hour TSP Monitoring Data
Month
2021/08
Monitoring Location :
AMS1N
Start Date
Weather
Condition
Action Level
Limt Level
Concentration
(ug/m
3
)
2021-08-05
Fine
153
260
40.4
2021-08-11
Fine
153
260
91.1
2021-08-17
Fine
153
260
21.6
2021-08-23
Fine
153
260
31.9
2021-08-27
Cloudy
153
260
31.6
Monitoring Location :
AMS2N1
Start Date
Weather
Condition
Action Level
Limt Level
Concentration
(ug/m
3
)
2021-08-05
Fine
179
260
53.4
2021-08-11
Fine
179
260
90.8
2021-08-17
Fine
179
260
29.2
2021-08-23
Fine
179
260
38.5
2021-08-27
Cloudy
179
260
38.9
Monitoring Location :
AMS3N
Start Date
Weather
Condition
Action Level
Limt Level
Concentration
(ug/m
3
)
2021-08-05
Fine
158
260
70.1
2021-08-11
Fine
158
260
85.3
2021-08-17
Fine
158
260
37.4
2021-08-23
Fine
158
260
46.2
2021-08-27
Cloudy
158
260
46.2
Monitoring Location :
AMS4N
Start Date
Weather
Condition
Action Level
Limt Level
Concentration
(ug/m
3
)
2021-08-05
Fine
146
260
73.9
2021-08-11
Fine
146
260
70.2
2021-08-17
Fine
146
260
50.1
2021-08-23
Fine
146
260
58.2
2021-08-27
Cloudy
146
260
58.5